Quick Summary
Managing track construction during the school year means planning work around the academic calendar with a phasing plan that maps tasks to planned work windows. Summer handles surface removal, base repairs, and installation, while fall and spring suit fencing, drainage tie-ins, and equipment work away from the running surface, and winter covers planning, procurement, and prep.
- New track surfaces need dry, warm conditions to cure, so the bulk of installation belongs in summer.
- Winter is the window for bids, scope, and budget controls, and late approvals push summer work.
- Hidden base damage adds days to early summer base and drainage work.
- Ask your contractor for their safety record in writing, since OSHA regulations set the baseline.
- Tell coaches which facilities will cover PE and team practice during the work.
Table of Contents
- Building a School Construction Phasing Plan Around the Academic Calendar
- School Construction Safety Plan: Separating Work Zones From Students
- School Construction Communication Plan for Staff, Families, and Coaches
- Frequently Asked Questions
Building a School Construction Phasing Plan Around the Academic Calendar
Managing track construction during the school year involves planning work around the school calendar. A track construction phasing plan maps tasks to planned work windows.
Three windows: summer for surface removal, base repairs, and installation; fall and spring for fencing, drainage tie-ins, and equipment work away from the running surface; winter for planning, procurement, and prep. New track surfaces need dry, warm conditions to cure, so the bulk of installation belongs in summer. Federal Highway Administration guidance on pavement placement weather limits explains how temperature and moisture affect surface work, and the same logic applies to track surfaces.
When you are ready to scope a project, build the track your program deserves and restore your track without the teardown both lay out the starting points.

| Project Phase | Best Window | What Happens | Watch For |
|---|---|---|---|
| Planning and procurement | Winter | Bids, scope, budget controls | Late approvals push summer work |
| Base and drainage work | Early summer | Repairs under the surface | Hidden base damage adds days |
| Surface installation | Mid summer | New surface laid and cured | Rain and cool nights delay curing |
School Construction Safety Plan: Separating Work Zones From Students
A school construction safety plan can describe how work zones are separated from student areas. Consider documenting site access, signage, and identified hazards.
Safety procedures can address site access, inspections, responsibility, and how concerns are raised. Bishop Kelly High School is a TDRATHLETICS customer.
OSHA construction safety and health regulations set the baseline for site safety, and your contractor should already meet it. Ask for their safety record in writing.
School Construction Communication Plan for Staff, Families, and Coaches
A school construction communication plan can outline how updates are shared and who receives them. Consider identifying a point of contact and communicating project timing to coaches.
Tell coaches which facilities will cover PE and team practice during the work. Before you hire anyone, see how we build tracks that build legacy.
Frequently Asked Questions
How do you manage track construction while school is in session?
Plan the project schedule around the school calendar. Discuss the proposed timeline and safety planning with the contractor before work begins.
How can a school phase track construction to reduce disruption?
Plan project stages and timing around the academic calendar. Discuss the proposed scope and schedule with the contractor before signing.
What safety measures should be in place during school track construction?
A school construction safety plan can address work-zone separation, site access, and communication about the work. Discuss safety planning with the contractor and school staff.
Track construction during the school year fails on scheduling and communication far more often than on the work itself. At TDRATHLETICS, our in-house crews handle both new construction and restoration, and we recommend what your surface actually needs rather than the most expensive option. Precision project delivery and honest recommendations keep your athletes training and your calendar intact. Get started with TDRATHLETICS and get a free assessment of your track before the next window closes.